Julian Pricepresented to the East of England branch in September 2003 on the installation of EDF's Energy high voltage suppliesat Heathrow. EDF Energy own, operate and maintain the existing high voltage network at Heathrow Airport.

Julian looked at the scope of work procured to ECC at Terminal 5. He examined the challenges that were facedand reviewed the procurement strategies. Julian concluded the session with his own views on how the project progressed.

Slides from Julian's presentation are available to download below.

Comments on this site are moderated. Please allow up to 24 hours for your comment to be published on this site. Thank you for adding your comment.
{{comments.length}}CommentComments
{{item.AuthorName}}

{{item.AuthorName}} {{item.AuthorName}} says on {{item.DateFormattedString}}:

Share this page

Recommended events

Event

Project Management Mythology

21 November 2017

Recommended blogs

Flash mob at Terminal 5

4 October 2016

Save for later

Favourite

Challenges and solutions for changing transport

25 May 2017

Transport brings significant benefits, but it also comes with huge costs, long lead times, and high intensity 24/7 operations, making it hard to change. What are your ideas for improving success?

Save for later

Favourite

Recommended news

Save for later

Favourite

Save for later

Favourite

Join APM

Sign up to the APM Newsletter.